Provisional Sums in Deep Space

How a provisional sum lives in Deep Space from the estimate to the final claim: the allowance on the head contract, the drawdowns spent against it, the internal approval route, the variations Deep Space raises when the allowance is exceeded or closed under, and where the money shows up in the Budget Register and the progress claim. Written for the Customer Success team and for anyone operating the Commercial module.

Deep Space Happens automatically Client-facing Click any screenshot to enlarge · ← → to step through · Esc to close

1The 60-second brief

A provisional sum is money the head contract sets aside for work that cannot be priced when the contract is signed. Deep Space keeps that money in two layers, and almost every question a customer asks comes down to which layer they are looking at.

TermWhat it isWhere you see it
Allowance The provisional sum as it is priced into the contract sum. One allowance has a title, a type (Provisional Sum, Prime Cost, Contingency or Other), one cost code and one or more priced lines. Head contract drawer → Provisional Sums tab; the Allowance column of the Provisional Sum Register.
Drawdown A priced request to spend against an allowance. An allowance can carry any number of drawdowns, numbered in order. Only approved drawdowns move money. The Provisional Sum Register (it is a register of drawdowns first) and the cards inside an allowance's drawer.
Drawn / Remaining Drawn is the sell value of approved drawdowns. Remaining is the allowance less Drawn and stops at zero: once the allowance is exceeded the excess is carried by a variation, not by a negative Remaining. Register columns and the drawer header.
Net adjustment What the provisional sum finally does to the contract sum: (actual cost + margin) − allowance. Positive is an over-run, negative is a saving handed back to the client. The Adjustment Summary card in the drawer, and the variation Deep Space raises.

The lifecycle in one line

Allowance is created (from the estimate or by hand) → the allowance is approved onto the head contract, which puts a line on the Schedule of Values → the team records drawdowns as the work is instructed → each drawdown is approved, directly or through an internal approval route → when approved drawdowns exceed the allowance, Deep Space raises a head contract variation for the over-run → when the work is finished the allowance is closed, and any saving goes back to the client as a credit variation.

Status words

SurfaceStatusMeaning
AllowanceUnapprovedExists in the register but is not yet part of the contract sum. Can be edited freely.
ApprovedOn the head contract. Its lines are on the Schedule of Values and drawdowns can be recorded against it. The allowance itself is now read-only in the drawer.
ClosedWork finished. No further drawdowns; any saving has been credited.
DrawdownDraftBeing prepared. Editable and deletable.
PendingSubmitted for internal approval, or waiting for a decision. Shows an amber In approval chip while the approval route runs.
ApprovedCounts towards Drawn; its lines flow to the Budget Register and the claim.
DeclinedRefused. A drawdown rejected by the approval route goes back to Draft instead, with an Approval rejected chip, ready to revise and resubmit.
Three rules that explain most behaviour

Only approved drawdowns move money. Draft and Pending drawdowns are visible everywhere but change nothing in the budget, the claim or the contract sum.

Within the allowance, nothing else is raised. Spending up to the allowance simply consumes it. Deep Space raises a variation only when approved drawdowns cross the allowance, and a credit only at close-out.

The cost code is set on the allowance, once. Drawdown lines inherit it. Deep Space refuses to approve an allowance, or to submit or approve a drawdown, while any line has no cost code, because the Budget Register would have nowhere to place the money.

Wording to watch

Inside Deep Space, "PS" on its own usually means Payment Schedule. Say "provisional sum" or "allowance" in full when talking to customers, and expect the UI to do the same.

The margin percentage on a line is a markup on cost. A 20% rate on a $1,000 cost gives a $1,200 sell, which is a 16.7% margin on sell. The line editor shows both figures.

A tour of the register

Commercial → Head Contract (Client) → Provisional Sum Register (it carries a BETA tag in the menu) opens the register. The subtitle says what it is: the drawdown register — spend recorded against the allowances attached to each head contract. Four cards across the top total the project: Total Allowances, Drawn, Remaining and the number of Drafts still to be dealt with. Two tabs switch the table between the two layers.

Provisional Sum Register, Allowances tab: one row per allowance with Allowance, Drawn, Remaining and Status columns
Allowances tab. One row per allowance: its ID, head contract, title, type, Allowance / Drawn / Remaining and the status chip. PS-Asher1-0018 is fully drawn (Drawn above Allowance, Remaining $0.00); the excess sits in the variation Deep Space raised, not here. New Allowance and New Drawdown live top-right; the search box takes a drawdown, allowance ID or head contract.
Provisional Sum Register, Drawdowns tab: one row per drawdown with Cost, Sell, Status and Actions
Drawdowns tab. One row per drawdown, numbered within its allowance (DD-01, DD-02 …), with the allowance and head contract it belongs to, Cost, Sell and Status. The Actions column changes with the status: a Draft offers Approve and Decline, a drawdown in an approval route shows In approval with View approval route, and a settled one offers Allowance to open its parent.

Click an allowance ID on either tab and its drawer opens on the right. Everything about one provisional sum is in that drawer, top to bottom:

  1. Header — ID, title and status, then Allowance / Drawn / Remaining and the blended margin of the allowance's lines. Close Allowance sits here and is only available once every drawdown is settled.
  2. Drawdowns — one card per drawdown with Add Drawdown above them. Each card shows the drawdown's lines (cost code, quantity and rate, cost, sell, margin) and its totals; a card in an approval route carries the amber approval panel.
  3. Adjustment Summary — the six lines from the original allowance to the net adjustment to the contract sum, under the contract's margin basis.
  4. Allowance Breakdown — the allowance's own lines as priced into the contract.
Allowance drawer open over the register: header cards, Close Allowance, Add Drawdown and the first drawdown cards
The allowance drawer. PS-Asher1-0019: $300 allowance, $84 drawn, $216 remaining, 16.7% margin. Two approved drawdowns and a third in approval.
Drawdown cards inside the drawer: two approved, one Pending with the In approval chip and the approval panel
Drawdown cards. #1 and #2 are Approved and count towards Drawn. #3 is Pending with the In approval chip: the panel names the step and the approver, and View approval route opens the route. It changes nothing until the final approver signs off.
Adjustment Summary card with six lines and the Allowance Breakdown below it
Adjustment Summary and Allowance Breakdown. Actual purchase cost $70 (the two approved drawdowns), builder's margin $14 at the contractual 20% on cost, net adjustment $0.00 because $84 is still inside the $300 allowance. The Pending drawdown is not in these figures.
Reading the two margin figures on one screen

The drawer header and the line cards show margin on sell (16.7%). The Adjustment Summary quotes the contractual rate on cost (20.0%). They are the same money: a $20 cost sold at $24 is 20% on cost and 16.7% on sell.

2One-time setup

Four things are decided before the first drawdown. Two of them (the margin basis and the contract's margin rate) are the settings that make one customer's provisional sums behave differently from another's, so get them right on day one: the basis locks on the contract at the first drawdown approval.

2.1 Choose the house default for the margin basis

The margin basis says where the builder's margin is applied when a provisional sum is adjusted. Both bases use the contract's provisional sum margin rate; they differ in what the rate is applied to.

BasisMargin termTypical contractEffect
On actual cost actual cost × rate AS4000-style: margin on the whole actual cost of the provisional work. Over-runs cost the client more; savings hand back less, because the margin shrinks with the cost.
On variance (actual cost − allowance) × rate Contracts where the allowance already carries margin and only the difference is adjusted. Smaller over-run adjustments; savings hand back more than the cost saving alone.

A worked example with the same allowance under both bases is in section 9. A margin rate of 0 is legitimate: it models contracts that pay the actual cost with no margin.

  1. Deep SpaceSet the house default
    Admin → Company Settings → Commercial tab → the Provisional Sums card → Provisional Sum margin basis (house default). Pick On actual cost or On variance and save. Every head contract that does not choose its own basis follows this. The card also states the instrument rule in one line: every drawdown that moves the contract sum raises a Head Contract Variation.
Company Settings, Commercial tab: the Provisional Sums card with the house-default margin basis select open
Company Settings → Commercial → Provisional Sums. The house default, with both bases in the select. The helper text under the field is the same explanation the customer reads.

2.2 Make sure the cost codes exist

Every allowance line carries one cost code, and drawdown lines inherit it. The code is what the Budget Register keys on, so it must exist before the allowance is approved onto the contract.

  1. Deep SpaceCheck the workspace cost codes
    Admin → Finance → Financial Model → Cost Codes tab. Confirm the trades the customer expects to run provisional sums against are present and not archived. The allowance form offers these codes in a picker (section 4 shows it); free text is not accepted.

2.3 Set the basis and the margin rate on the head contract

The contract carries the contractual provisional sum margin percentage (the Annexure figure) and may override the house default basis. Both fields sit in the head contract form.

  1. Deep SpaceOpen the contract form
    Commercial → Head Contract (Client) → Head Contract Register → New Contract, or the pencil icon on an existing contract to open Edit Head Contract. Both fields sit in Contract Basics.
  2. Deep SpaceProvisional Sum Margin Basis
    Leave Workspace default (…) to follow the house default, or pick On actual cost / On variance for this contract only. Once the contract has an approved drawdown the select is disabled and reads Locked — a drawdown has been approved on this contract.
  3. Deep SpaceProvisional Sum Rate (% on cost)
    Enter the contractual percentage for profit and attendance. The label says it: the rate is applied on cost, so 20 means sell = cost × 1.20 (a 16.7% margin on sell). On actual cost it prefills every new allowance and drawdown line; on variance it grosses up the over-allowance difference. The estimator can still change a line's rate before approval.
New Head Contract form: Provisional Sum Margin Basis select open and the Provisional Sum Rate (% on cost) field
New Head Contract. Provisional Sum Margin Basis with its three options, and Provisional Sum Rate (% on cost) with the form's own worked line: 20 means sell = cost × 1.20.
Edit Head Contract for a contract with an approved drawdown: the basis select is disabled and marked Locked
After the first approved drawdown. CON-Asher1-0010: the basis is greyed out and reads "Locked — a drawdown has been approved on this contract". The rate stays editable.
The basis locks, the rate does not

The first approved drawdown on a contract freezes its margin basis for good; every later adjustment on that contract uses the same basis, so the contract sum never changes shape half-way. The margin rate stays editable, and each drawdown line keeps the rate it was approved with.

An individual allowance can override the contract's basis under Edit Allowance → Advanced. Deep Space requires a written reason for the override; use it for the odd clause, not as a habit.

2.4 Optional: route drawdown approvals through Delegation of Authority

By default anyone with access to the register approves a drawdown with one click. Customers who want authority limits switch the internal approval route on by configuring a workflow; nothing else needs turning on.

  1. Deep SpaceCreate the workflow
    Admin → Finance → Delegation of Authority → Approval Workflows tab → Add Workflow with Entity Type PS Drawdown (the entity type cannot be changed after creation). Each step is either a Fixed role or DoA-driven, where the engine routes by the drawdown's sell amount through the Approval Thresholds matrix; the threshold simulator on the right previews which steps a given amount activates. Only one PS Drawdown workflow can be Active per scope.
  2. Happens automaticallyThe gate is now on
    From the moment the workflow is active, Approve on a drawdown answers Internal approval required and offers Submit for approval instead. Workspaces without a PS Drawdown workflow keep one-click approval. Section 6 walks the route.
Delegation of Authority, Edit Workflow Template: entity type PS Drawdown, Active on, one DoA-driven step
Delegation of Authority → Approval Workflows. The PS Drawdown workflow on the demo workspace: Active, one DoA-driven step routed through the Approval Thresholds matrix.

3Where allowances come from

An allowance reaches the register by one of two roads. Most arrive from the estimate: a BOQ line typed as a provisional sum becomes a Draft allowance the moment the budget is pushed. The rest are typed in by hand, either in the register or on the head contract. Both roads end in the same place: an Unapproved allowance that still needs a head contract and an approval (section 4).

3.1 From the estimate

  1. Deep SpaceType the BOQ line
    In Estimation, when adding or editing a BOQ item, set Item Type to PS, PC or Contingency (the default is Lump Sum). The line then carries an amber type chip in the BOQ, and the estimate's Allowances card counts it: "{n} PS / PC / Contingency items".
  2. Happens automaticallyZero margin by default
    Typed lines price at cost with no margin, because the contract normally states profit and attendance on provisional sums separately. Bulk pricing skips them ("20 items updated · skipped 4 PS / PC / Contingency") unless the estimator ticks "Also price the … PS / PC / Contingency lines in this selection"; pricing one by hand is recorded as an Override.
  3. Deep SpacePush the budget
    Estimation → Push to Budget Register, or Commercial → Budget Register → Generate Budget Register. The success toast ends with the seeding result: "PS sync: 3 created, 0 updated, 1 skipped, 0 orphaned."
  4. Happens automaticallyOne Draft allowance per typed line
    Each typed BOQ line becomes its own allowance: title = the BOQ item name, type = the item type, one line carrying the BOQ quantity, unit, cost rate and sell, and the BOQ line's cost code if it had one. The description reads "Seeded from Estimation Budget push." No head contract is set, so the register shows the allowance as Unassigned and the head contract's Provisional Sums tab lists it under Unassigned Draft Provisional Sums.
  5. Happens automaticallyKept out of the budget until approved
    Typed lines are excluded from the Original Budget. The Budget Register shows an amber banner, "Draft Provisional Sums not in budget: $… · n drafts · n unassigned", and a Draft Provisional Sums table on the cost code's Variations tab. Their money enters the budget only through approved drawdowns (section 8).
Pushing again is safe

Seeding is keyed on the BOQ line. A second push updates the existing Draft in place (updated), leaves an allowance that has already been approved alone (skipped), and reports a Draft whose BOQ line has since been removed as orphaned without deleting it. The Refresh Data button on the Budget Register also seeds, but its toast does not report the count.

Estimation BOQ Builder: line 1 Project Management (38hr week) typed PS, cost code CC-100-10 Consultants, 6 ea at $4,800, markup and margin 0.0%
Estimation → BOQ Builder. Line 1, Project Management (38hr week), is typed PS: 6 ea × $4,800 = $28,800 at 0.0% markup and 0.0% margin, while the Lump Sum lines below carry 15%. This one line became PS-Asher1-0004 when the budget was pushed.
Edit Item modal with Item Type set to PS and Markup on cost / Margin on sell at 0.0
Edit Item. The Item Type select sits under the cost code; with PS chosen, Markup on cost and Margin on sell read 0.0 — the zero-margin default.
Budget Register with the amber banner Draft Provisional Sums not in budget: $28,920.00 · 2 drafts · 0 unassigned, and the Approved PS Cost / Pending PS Cost columns
Commercial → Budget Register. The amber banner, Draft Provisional Sums not in budget: $28,920.00 · 2 drafts · 0 unassigned, is the cost of the two Unapproved allowances (PS-Asher1-0004's $28,800 and PS-Asher1-0021's $120). The Approved PS Cost and Pending PS Cost columns beside Revised Budget are where approved and in-flight drawdown lines land (section 8).

3.2 By hand

  1. Deep SpaceOpen the form
    Provisional Sum Register → New Allowance, or open the head contract → Provisional Sums tab → Add Provisional Sum (this one pre-selects the contract). Either way the form creates a Draft; the header says so: "Creates a Draft. Approve it from the drawer or the head contract's Provisional Sums tab to add it to the contract sum."
  2. Deep SpaceTitle, Type, Head contract
    Title is the only required field. Type offers Provisional Sum, Prime Cost, Contingency or Other. Head contract can be left on Assign later, but until a contract is chosen the form warns "No head contract yet — lines stay unpriced until one is chosen"; once chosen it shows the contract's terms, e.g. "Rate 20 % on cost · margin on actual cost", and new lines prefill that rate.
  3. Deep SpaceDescription (optional)
    + Add a description opens a note for the team. It is not printed on the SOV, the claim or the PDF; the line description is what the client sees.
  4. Deep SpaceLines
    Each line card has a cost code button (Select cost code opens the picker; free text is not accepted), a description ("the line's name on the contract SOV, claims and the claim PDF"; with a single line it defaults to the title), and the money row Qty · Cost rate · Cost · Markup % · Margin % · Sell rate · Sell. Type any two of cost, markup or margin and the rest follows. + Add line starts the next line on the same cost code: "One cost code per allowance by default."
  5. Deep SpaceCreate Draft
    The footer totals show Cost, Sell and Margin ("0 % · passthrough" for a cost-only allowance). Create Draft → toast "Draft provisional sum created". The allowance appears as Unapproved and can be edited freely until it is approved.
Giving a seeded allowance its contract

Open the head contract → Provisional Sums tab → Unassigned Draft Provisional Sums → Assign here (toast "Provisional sum assigned"), or open the allowance in the register and pick the contract in Edit Allowance. Approval is impossible without one: the button reads "Assign a head contract first".

New Provisional Sum form: title Asher COM-662 Final 1, type Provisional Sum, head contract CON-Asher1-0010 with Rate 20 % on cost · margin on actual cost, one line on CC-7142 at 1 × $1,000 cost, markup 20, sell $1,200
New Allowance. Head contract CON-Asher1-0010 chosen, so the form shows the contract's terms, Rate 20 % on cost · margin on actual cost, and the line prefilled that rate: $1,000 cost, markup 20 → margin 16.7, sell $1,200. The description placeholder reads Defaults to "Asher COM-662 Final 1". Footer: Cost $1,000 · Sell $1,200 · Margin 16.7 %.
Select cost code picker over the New Allowance form, CC-7142 Asher Test Cost Code 001 selected
Select cost code. The picker lists the workspace's codes with a search box; one selected, Apply.
Allowances tab with PS-Asher1-0022 showing an Unassigned chip in the Head Contract column and status Unapproved
Saved with "Assign later". PS-Asher1-0022 appears at the top as Unapproved with an amber Unassigned chip where the contract should be; the Drafts card went from 2 to 3.
CON-Asher1-0010 drawer, Provisional Sums tab: four allowances with a Variations column, and the amber Unassigned Draft Provisional Sums section listing PS-Asher1-0022 with Assign here
Head contract → Provisional Sums tab. The contract's own allowances on top (note PS-Asher1-0018's HVO-Asher1-0022 · +$120.00 in the Variations column — section 7), and below them the amber Unassigned Draft Provisional Sums list with Assign here.

4Approving an allowance onto the contract

Approving an allowance answers one question: is this money part of the contract? It is a single action on the whole allowance, it needs no approval route, and it does not spend anything. Spending is what drawdowns are for (section 5).

  1. Deep SpaceCheck the three prerequisites
    A head contract is assigned, there is at least one line, and every line has a cost code from the picker. Without a contract the button is disabled ("Assign a head contract first"); without a code Deep Space refuses with "Allowance line 2 needs a cost code from the project's cost structure before it can be approved".
  2. Deep SpaceApprove Allowance
    Open the allowance's drawer (register) or find it on the contract's Provisional Sums tab and click Approve Allowance. There is no confirmation dialog; the toast reads "Allowance approved — it now counts toward the contract sum" and the chip turns Approved.
  3. Happens automaticallyLines land on the Schedule of Values
    Each allowance line becomes a row on the head contract's Schedule of Values at its sell value, tagged as a provisional sum. In the SOV preview the row carries an amber PS badge; it turns green PS · ACTIVE once the first drawdown against it is approved. The allowance is now in the contract sum, but the row cannot be claimed until a drawdown activates it: the claim forms show it as Pending approval with a claim value of zero.
  4. Happens automaticallyThe drawer becomes read-only
    The Edit Allowance panel disappears; the drawer now shows Drawdowns with Add Drawdown, the Adjustment Summary and the Allowance Breakdown. Lines and pricing are fixed on the contract from here on.
Drawer of PS-Asher1-0022, Unapproved: Approve Allowance and Decline Allowance above the Edit Allowance panel with title, type, head contract, Advanced margin basis override and the line editor
An Unapproved allowance's drawer. Approve Allowance and Decline Allowance at the top; below, the Edit Allowance panel with the contract facts line, the collapsed Advanced — margin basis override, the line editor and the footnote "Lines can be changed while the allowance is unapproved; approving it fixes them on the contract."
CON-Asher1-0010 Details tab, Schedule of Values Preview: three rows badged PS · ACTIVE, one badged PS, and the newly approved Asher COM-662 Final 1 badged PS
Head contract → Details → Schedule of Values Preview, right after approving PS-Asher1-0022. Its line Asher COM-662 Final 1 is the new bottom row, $1,200 with the amber PS badge. Above it, PS-Asher1-0018's and 0019's rows read PS · ACTIVE because drawdowns have been approved against them; PS-Asher1-0020's $120 row is still plain PS. The rows are named after their line descriptions — which is why the older ones all say "Test".

Declining instead

Decline Allowance on an Unapproved allowance marks it and its lines Declined (toast "Allowance declined"). A declined allowance stays in the register for the record and cannot be revived; if the money is needed after all, create a new allowance. An approved allowance is not declined but closed (section 7), and only once every drawdown on it is settled.

The margin basis override

While an allowance is Unapproved, Edit Allowance → Advanced — margin basis override lets it depart from the contract's basis: Contract default, Override: on actual cost or Override: on variance, with a reason that Deep Space insists on. The drawer then shows a chip such as "Margin basis override: on variance — {reason}". Use it for the odd clause that treats one allowance differently; the setting cannot be changed once the allowance has produced an adjustment.

Two words for the same step

Older copy calls this step attaching: the Budget Register still says Draft allowances are excluded "until attached", and the backend's messages use the word too. Attached and approved mean the same thing for an allowance. Say approved to customers.

5Recording and approving drawdowns

A drawdown is the priced request to spend part of an approved allowance. It is born as a Draft, can be edited until it is approved, and only its approval moves money: into Drawn, into the Budget Register and onto the claim. Everything in this section happens in the Provisional Sum Register.

5.1 Record a drawdown

  1. Deep SpaceOpen the form
    Register → New Drawdown opens New Drawdown — pick an allowance: every approved allowance with its head contract and "{remaining} remaining of {allowance}". Or open the allowance's drawer and click Add Drawdown. The form's header restates the target: "Against PS-Asher1-0019 · COM-805 Test 2 — remaining $216.00 of $300.00 · CON-Asher1-0010 · rate 20 % on cost".
  2. Deep SpaceTitle and lines
    Title is required ("What this drawdown pays for"); the description is optional and shows only on the drawdown card. Each line has the same money row as an allowance line: Qty · Cost rate · Cost · Markup % · Margin % · Sell rate · Sell, plus a checkbox "Additional procurement cost — freight, craneage, storage; feeds summary lines 4 / 5" for costs that are not the work itself.
  3. Happens automaticallyCost code and rate are inherited
    The line carries the allowance's cost code without asking: "Cost code: inherited from the allowance (CC-7142 - Asher Test Cost Code 001)." A link, "Code this drawdown to a different cost code", exposes the picker for the exception. Under On actual cost the line prefills the contract's rate; under On variance it prefills as cost passthrough (sell = cost), because that basis adds margin only on the over-allowance difference.
  4. Deep SpaceRead the totals, then Create Drawdown
    The footer shows Cost, Sell, Margin and Remaining after — what the allowance will have left once this drawdown is approved. If the sell exceeds what is left, it turns into "Over the remaining allowance by $…" with the warning "A Head Contract Variation will be raised for the over-run when this drawdown is approved." Create Drawdown → toast "Drawdown created"; the drawdown is Draft, numbered DD-01, DD-02 … within its allowance.
Two checks that can interrupt the save

Margin check — the drawdown's effective margin does not match the contract: "Effective margin 12.5% is below the contractual 20% — the builder loses margin on this drawdown.", the mirror-image "…is above the contractual 20% — this exceeds the contractual entitlement and may be disputed at the final account.", or, on an on-variance contract, "drawdown lines should be cost-passthrough (sell = cost), or the client is charged margin twice." Save anyway proceeds; it is advice, not a block.

Over the remaining allowance — "This drawdown exceeds the remaining allowance by $…. When approved, a Head Contract Variation will be raised for the over-run and issued for approval." Continue saves it; the variation is raised at approval, not now (section 7).

New Drawdown — pick an allowance: approved allowances listed with remaining of allowance, PS-Asher1-0022 first with $1,200 remaining of $1,200
Pick an allowance. Every approved allowance with its head contract and remaining of figure; PS-Asher1-0022 has its full $1,200 left, PS-Asher1-0018 shows $0.00 remaining of $1,200.
New Drawdown form freshly opened against PS-Asher1-0022: context line, empty title, one line prefilled with markup 20 / margin 16.7, inherited cost code note, Remaining after $1,200
The form opens against it. The context line restates the target; the first line is already on Markup 20 / Margin 16.7 from the contract, the note under the lines reads Cost code: inherited from the allowance (CC-7142 - Asher Test Cost Code 001), and the footer shows Remaining after $1,200.00 before anything is typed.
New Drawdown form filled: title Asher COM-662 Final DD1, cost rate 300, cost $300, sell $360, footer Cost $300 · Sell $360 · Margin 16.7 % · Remaining after $840
Filled in. Cost rate 300 gives Cost $300 and Sell $360 at the inherited 20%; the footer now reads Remaining after $840.00. The description placeholder defaults to the drawdown's title.
New Drawdown form with cost 1,500 and sell 1,800: footer shows Over the remaining allowance by $600.00 and the variation warning
Over the allowance. With cost 1,500 the sell is $1,800 against $1,200 remaining: the footer turns to Over the remaining allowance by $600.00 with A Head Contract Variation will be raised for the over-run when this drawdown is approved.
Over the remaining allowance dialog: This drawdown exceeds the remaining allowance by $600.00 … Cancel / Continue
The dialog on Create Drawdown. Continue saves the drawdown as a Draft; nothing is raised until it is approved.

5.2 While it is a Draft

The drawdown card offers Edit (opens Edit Drawdown #n, Save Changes) and Delete (no confirmation; toast "Drawdown deleted"). Both exist only while the drawdown is a Draft: once it is Pending it sits with the approver, and once Approved it is part of the record.

Allowance drawer after Drawdown created: card #1 Asher COM-662 Final DD1, Draft, with Approve, Decline, Edit and Delete
A Draft drawdown card right after the Drawdown created toast: #1 · Asher COM-662 Final DD1 with its line, totals and the four actions. Drawn is still $0.00 and Close Allowance is disabled while the drawdown is unresolved.

5.3 Approve or decline

  1. Deep SpaceApprove
    On the drawdown card, or in the Drawdowns tab's Actions column, click Approve. No confirmation; toast "Drawdown approved". On a workspace with a PS Drawdown approval workflow, this click answers Internal approval required instead — section 6.
  2. Happens automaticallyWhat one approval does
    The drawdown's sell joins Drawn and Remaining falls. Its lines reach the Budget Register on their cost code as approved provisional sum cost. The allowance's SOV row turns PS · ACTIVE and becomes claimable up to what has been drawn. The contract's margin basis locks if this was its first approved drawdown. And if cumulative approved spend now exceeds the allowance, the over-run variation is raised (section 7).
  3. Deep SpaceDecline
    Decline marks a Draft or Pending drawdown Declined (toast "Drawdown declined"). It stays on the ledger for the record. An approved drawdown cannot be declined: "Approved drawdowns cannot be declined; the revoke flow is not available yet", and one whose over-run is already carried by a variation points you to that variation instead: "dispute that variation instead; it reverts the drawdown automatically."
Drawer after the drawdown was approved: Drawn $360, Remaining $840, card #1 Approved, Adjustment Summary with Original allowance $1,200, Actual purchase cost $300, Builder's margin $60, net adjustment $0.00
After approval. The header cards move to Drawn $360.00 · Remaining $840.00, the card reads Approved, and the Adjustment Summary appears: original allowance $1,200, actual purchase cost $300, builder's margin $60 (20% on cost), net adjustment $0.00 because $360 is still inside the allowance. The register's Drawn total rose by the same $360.
The cost-code gate, again

Approve and Submit for approval both refuse a drawdown whose line has no recognised cost code: "Every drawdown line needs a cost code from the project's cost structure before it can be approved — 1 line has none or an unrecognised code. Edit the drawdown and pick the cost code on each line." In practice this only happens when the allowance itself has no code (legacy records): new lines inherit.

6Internal approval through Delegation of Authority

On a workspace with an active PS Drawdown workflow (section 2.4), a drawdown is not approved by whoever clicks first. It is submitted, routed to the approver the workflow names for its amount, and the final approver's sign-off is the approval: nobody comes back to click Approve a second time.

  1. Deep SpaceSubmit for approval
    Click Approve on the drawdown as usual. Deep Space answers with Internal approval required: "This workspace routes PS drawdown approvals through the Delegation of Authority workflow. Submit this drawdown for internal approval? The final approver's sign-off will approve the drawdown." Confirm with Submit for approval → toast "Drawdown submitted for internal approval".
  2. Happens automaticallyThe route opens
    The drawdown becomes Pending with an amber In approval chip; Approve, Decline, Edit and Delete disappear. The amount routed is the drawdown's sell total. A DoA-driven step picks its approver from the Approval Thresholds ladder; a fixed-role step goes to that role. Approvers are notified.
  3. Deep SpaceThe approver acts from the register…
    The card and the Drawdowns tab show the approver "Awaiting your approval — approving here approves the drawdown" and a green Review & approve. It opens the Approval Route: the steps, who is on each, a Comment (optional) box, and Approve / Reject.
  4. Deep Space…or from My Approvals
    The My Approvals icon in the top bar (its badge counts the requests waiting on you) opens the approvals inbox as a side panel; the same inbox is a page at /auth/horizon/my-approvals. The request is listed as "PS Drawdown DD-01" with the project and date, and the notification email's link opens the allowance's drawer in the register with the card in view.
  5. Happens automaticallyApproved: the drawdown approval runs
    When the last step is approved, Deep Space executes the drawdown approval itself, with every effect from section 5.3: Drawn, budget, SOV activation, basis lock, over-run variation. The register refreshes to Approved. The approver's name is recorded as the one who approved the drawdown.
  6. Happens automaticallyRejected: back to Draft
    A rejection returns the drawdown to Draft with a red Approval rejected chip. Edit it and click Approve again to submit a fresh request; the earlier one stays in the approval history.

Everyone else sees the card read-only: "Awaiting internal approval — the final approver's sign-off approves this drawdown", a View approval route button and the route's progress line, e.g. "Step 1 of 1 · Test · Asher DoA Test Project Manager" (figure under section 1). While the request is open, Decline is refused with "This drawdown has an internal approval in progress — revoke or resolve it in the approvals centre before declining."

Workspace workflow or project workflow

The route modal may open with an amber note: "This project has no Delegation of Authority of its own yet, so the workspace default was used. Configure it under Delegation of Authority with this project selected." A PS Drawdown workflow can be defined for the whole workspace or overridden per project; the note simply says which one is routing this drawdown. It is information, not an error.

Highest Authority override

A holder of the workspace's Highest Authority role who is not on the step sees "You are not an approver on this step, but you hold Highest Authority — you can override it." The buttons become Override Approve / Override Reject and a comment is required. The override is recorded in the approval history like any other decision. Nothing stops a submitter from approving their own drawdown if their role is on the step; that is deliberate for small commercial teams.

If the register still says In approval after the final Approve

The approval itself is recorded the moment the approver acts; updating the drawdown is a second step that can occasionally fail. Refresh the register first. If the chip persists, the Approval Route shows a red banner saying the record's status could not be updated automatically; the approval is not lost — contact support to apply it.

Internal approval required dialog over the register: This workspace routes PS drawdown approvals through the Delegation of Authority workflow … Cancel / Submit for approval
Internal approval required. What Approve answers with on a workspace that has an active PS Drawdown workflow.
Approval Route modal: project uses the workspace default note, step Test In Review, Highest Authority override banner, Comment (required for override), Override Approve / Override Reject
Approval Route, seen by a Highest Authority holder who is not on the step: the step Test is In Review, the override banner explains the rule, the comment becomes required and the buttons read Override Approve / Override Reject. An approver who is on the step sees plain Approve / Reject with an optional comment. Behind the modal, the drawdown card shows Pending · In approval and the read-only panel with Step 1 of 1 · Test · Asher DoA Test Project Manager.
Approval Route modal with the comment Test entered and Override Approve highlighted
Overriding. With a comment entered, Override Approve completes the route and Deep Space executes the drawdown approval (figure under section 5.3 shows the result).
Approval Route modal with the comment Test entered and Override Reject highlighted
Rejecting. Override Reject (or a step approver's Reject) closes the route against the drawdown.
Drawdown card back in Draft with the red Approval rejected chip and Approve, Decline, Edit, Delete available again
Back to Draft. The card carries the red Approval rejected chip and all four actions return; Drawn is unchanged at $0.00. Approve again to submit a fresh request.

7Over-runs and close-out

A provisional sum changes the contract sum in exactly two moments, and Deep Space records both with the instrument the client already knows: a Head Contract Variation. Spending inside the allowance raises nothing. The moment approved spend crosses the allowance, an over-run variation is raised; when the allowance is finally closed under, a credit variation hands the difference back. Neither is typed by anyone: the drawdown approval and the close-out create them.

7.1 The over-run variation

  1. Happens automaticallyRaised at the approval that crosses the line
    When a drawdown approval takes the allowance's net adjustment above zero, Deep Space raises a variation on the head contract for that net figure — not for the whole drawdown. It is born Submitted (the drawdown approval is the submission) and titled "PSO · PS-Asher1-0018 · DD-04 — Test COM-805", with the description ending "provisional sum over-run — net over-allowance drawdown (AS4000 cl.3 / NZS3910 cl.12 treatment)".
  2. Happens automaticallyLater drawdowns revise it, or add to it
    While that variation is still unapproved, the next over-run drawdown revises it to the new cumulative figure. Once the client has approved it, the next drawdown raises a delta variation for the increment only. Either way the sum of the variations equals the allowance's net adjustment — the drawer's footer says so: "Carrying the full +$120.00 net adjustment to the contract sum".
  3. Client-facingThe client approves the variation
    From here the variation lives its ordinary life in Commercial → Head Contract (Client) → Variations (Client-Side): it is issued, and the client approves or disputes it. Only Approved moves the contract sum. The variation document carries a Provisional Sum Adjustment section with the six-line build-up (or a folded version on sell-only templates).

Where the link shows

Worked example — PS-Asher1-0018

Allowance $1,200 sell. Four drawdowns approved: $120, $120, $360 and $720 sell (cost $100, $100, $300, $600). Cumulative cost $1,100; margin on actual cost at 20% = $220; net adjustment = $1,100 + $220 − $1,200 = +$120. DD-04 was the approval that crossed the line, so HVO-Asher1-0022 was raised for +$120.00 and is listed against DD-04. Drawn shows $1,320, Remaining $0.00.

PS-Asher1-0018 drawer: DD-04 card with Raised HVO-Asher1-0022 Submitted, the Variations raised by this allowance block (+$120.00 · DD-04) and the Adjustment Summary ending in net adjustment $120.00
PS-Asher1-0018's drawer. The DD-04 card reads Raised HVO-Asher1-0022 · Submitted; the Variations raised by this allowance block lists it at +$120.00 · DD-04 with the footer Carrying the full +$120.00 net adjustment to the contract sum; the Adjustment Summary shows how the $120 arises: $1,100 actual + $220 margin − $1,200 allowance.
Variations (VO) register with Source set to From provisional sums (PSO / PSC): rows carry PSO or PSC pills with From PS-… · DD-nn or Close-out credit · PS-… labels
Variations (Client-Side), Source = From provisional sums. HVO-Asher1-0022 carries the PSO pill with From PS-Asher1-0018 · DD-04; HVO-Asher1-0023 the PSC pill with Close-out credit · PS-Asher1-0017 and a negative value. Older PS-born variations on this project keep the description format they were created with; the pills are derived from the link, not from the text.
HVO-Asher1-0022 sidebar, Scope & Pricing tab: PSO pill, Raised from allowance PS-Asher1-0018 · Test COM-805 · Drawdown #4, Adjustment Summary, one scope line PSO · PS-Asher1-0018 · DD-04 at sell $120
The variation's own view. Raised from allowance PS-Asher1-0018 · Test COM-805 · Drawdown #4 links back to the register; the same Adjustment Summary follows, ending This variation carries $120.00 of the net adjustment; the single scope line is the PSO reference at $120 sell.

7.2 If the client disputes

Disputing a PS-born variation does more than mark it: Deep Space reverts the drawdown that raised it from Approved back to Pending, recomputes Drawn and Remaining, and the variation stops carrying any adjustment. The drawer says "Reverted to Pending — its variation was disputed" on the card, and the variations block strikes the value through with the note "Disputed — its drawdown was reverted to Pending". Because of this link, two things are refused: declining an approved drawdown whose over-run is already carried ("dispute that variation instead; it reverts the drawdown automatically"), and reverting a PS-born variation to Draft ("This variation was generated by a provisional sum drawdown and cannot be reverted to Draft. Dispute it instead.").

7.3 Closing the allowance

  1. Deep SpaceSettle every drawdown first
    Close Allowance (drawer header, or Close on the contract's Provisional Sums tab) stays disabled with "Resolve {n} outstanding drawdowns first" until no drawdown is Draft or Pending.
  2. Deep SpaceConfirm
    The dialog Close allowance: "Close this allowance? No further drawdowns can be recorded, and if it closed under, the difference is credited back to the contract sum." Confirm → toast "Provisional sum closed"; the chip reads Closed and Add Drawdown disappears.
  3. Happens automaticallyThree possible outcomes
    Closed under (net adjustment negative): a credit variation is raised for the difference, titled "PSC · PS-Asher1-0017 — Allowance D" with a negative value, and shown in the register as Close-out credit · PS-Asher1-0017. Exactly on (net zero): nothing is raised. Already over: the over-run variation already carries the adjustment, so closing only fixes the status.
Close allowance dialog over the PS-Asher1-0022 drawer: Close this allowance? No further drawdowns can be recorded, and if it closed under, the difference is credited back to the contract sum.
Close allowance. Over PS-Asher1-0022 with $360 drawn of $1,200: confirming here would close it under and raise a PSC credit of −$840 (= $300 actual + $60 margin − $1,200).
PS-Asher1-0017 drawer, Closed: Drawn $0.00, one Declined drawdown, Variations raised block with HVO-Asher1-0023 Submitted −$14,300.00, Adjustment Summary net adjustment −$14,300.00
A closed-under allowance. PS-Asher1-0017 closed with nothing drawn (its only drawdown was declined), so the whole $14,300 allowance is handed back: HVO-Asher1-0023 at −$14,300.00, footer Carrying the full −$14,300.00 net adjustment, and the six lines show $0 actual, $0 margin, −$14,300 net.
Variations register row for HVO-Asher1-0023: PSC pill, Close-out credit · PS-Asher1-0017, cost −$11,440, sell −$14,300, Submitted
The same credit in the Variations register. PSC pill, Close-out credit · PS-Asher1-0017, sell −$14,300 and cost −$11,440 (the allowance's cost at 20% on cost), status Submitted until the client approves it.
Savings hand back the margin too

Under On actual cost the credit is not just the unspent cost: a $10,000 allowance closed at $7,000 actual with 10% margin credits $2,300 (= $7,000 + $700 − $10,000), because the builder's margin shrinks with the cost. Under On variance the same case credits $3,300. Section 9 works both bases side by side.

8Budget Register and progress claims

Provisional sum money reaches the rest of the Commercial module through two doors: approved drawdown lines feed the Budget Register on their cost code, and activated allowance rows on the Schedule of Values feed the progress claim up to what has been drawn. The over-run itself travels as a variation and is claimed like one.

8.1 Budget Register

ColumnWhat it holdsTooltip in the register
Approved PS CostCost of the lines of approved drawdowns, grouped by the line's cost code.Cost of approved Provisional Sum lines.
Pending PS CostCost of drawdown lines still Pending (for example in an approval route). Forecast only.Forecast-only cost of attached Provisional Sum lines not yet approved.
Revised BudgetOriginal + Approved HC VO Cost + Approved PS Cost + Budget Changes.as stated
Projected BudgetRevised + Pending HC VO Cost + Pending PS Cost.as stated

Expand a cost code and open its Variations tab for the detail: a Provisional Sums (n) card lists the allowances contributing to the two columns with their Approved Cost and Pending Cost, and an amber Draft Provisional Sums (n) card lists Unapproved allowances that are visible for tracking but "excluded from Revised and Projected Budget totals until attached". The over-run variation does not add its cost a second time under head contract variations: the drawdown lines are the cost's only home.

Check the "View As" lens before comparing numbers

The Budget Register opens on View As: PM, and that lens scales every money column, provisional sums included: PM shows 90%, CA 81%, JCA 73%, and only View As: CM shows the register at face value. On Asher1, CC-7142's approved drawdown lines total $1,370 and its pending line $60; the PM view prints them as $1,233 and $54. Before telling a customer the register "does not match" the Provisional Sum Register, switch the lens to CM.

8.2 Progress claims

  1. Deep SpaceSection C in a new claim
    Commercial → Head Contract (Client) → Progress Claims (to client) → New Claim. After the SOV and the variations, Section C · Provisional Sums lists the allowance rows with a Provisional Sum chip and the count "{n} active, {n} pending".
  2. Happens automaticallyClaimable only up to what is drawn
    An allowance row can be claimed up to the lesser of the allowance and the approved drawdowns against it — Drawn is the cap. A row with no approved drawdown yet shows the chip Pending approval, a disabled tick and the claim cell "Zero until approved". Anything above the allowance is claimed through the approved over-run variation in the Variations section, not here — and only once the client has approved that variation; while it is Submitted the Variations section lists it as Pending (needs approval).
  3. Deep SpaceEdit, detail, PDF
    The edit form has the same Provisional Sums section ("{x} of {n} claimed · GST excl.") and a Provisional Sums subtotal; the claim detail shows Provisional Sums ({n} items) · Allowances & adjustments · GST excl.; the claim PDF prints a Provisional Sums section with Cost Code · Description · Allowance · Previous · This Period · Total · Status and rolls it into summary row C · Provisional Sums. The grand total caption reads Contract SOV + Approved Variations + Provisional Sums.
Two messages a claimer can hit

Claiming against an allowance row before any drawdown is approved: "claim_value must be 0 until the provisional sum line is approved". Claiming past the drawn cap: a range message quoting the line's allowed values. Both come straight from the server and mean the same thing — approve the drawdown first, or claim the over-run through its variation.

New Progress Claim – Head Contract on CON-Asher1-0010 (Active): claim period, dates, claim type Progress claim (SOV), an informational list of subcontract variations not covered
New Progress Claim. The head contract must be Active to be claimable (CON-Asher1-0010 was a Draft contract until it was activated for this capture). Claim period, dates and type as usual; the amber list of uncovered subcontract variations is informational.
SOV Items of the new claim: Variations section with HVO-Asher1-0022 PSO Pending (needs approval); Provisional Sums section 4 active, 1 pending, rows with Provisional Sum chips, Remaining equal to the drawn cap, a Pending approval row reading Zero until approved, subtotal $2,820.00
Section C · Provisional Sums — 4 active, 1 pending. Every activated allowance row carries the Provisional Sum chip and a Remaining equal to its drawn cap: PS-Asher1-0018's row $1,200 (fully drawn), PS-Asher1-0022's $360, PS-Asher1-0019's two rows $84 each. PS-Asher1-0020's row is Pending approval · Zero until approved — no drawdown approved yet. Above, the Variations section shows the over-run HVO-Asher1-0022 as PSO · Pending (needs approval): not claimable until the client approves it. Note the two $84 rows: the cap is applied per row today, so a two-line allowance offers its drawn amount twice — known issue COM-1109 (section 11).

Forecasting and the Financial Summary have no provisional-sum view of their own; they read the budget columns and the claims above.

Budget Register, View As: PM, category Asher Test 001 expanded: cost code CC-7142 with Approved PS Cost $1,233.00, Revised Budget $10,842.30, Pending PS Cost $54.00 and the chip 2 Approved / 0 Pending
Budget Register, cost code CC-7142. Approved PS Cost $1,233.00 and Pending PS Cost $54.00 under the PM lens — the ledger's $1,370 and $60 at 90%. The chip 2 Approved / 0 Pending counts head contract variations on the code, not drawdowns.
Cost code panel for CC-7142, Variations tab: Head Contract Variations (2), Provisional Sums (4) listing four allowances as Pending with Pending Cost, and Draft Provisional Sums (1) showing a raw head contract id
The cost code's Variations tab. Head Contract Variations (2) above, Provisional Sums (4) and the amber Draft Provisional Sums (1) below. Read the two provisional-sum tables with care: today they list the allowance lines on this code by the allowance's own status, so they do not reconcile to the drawdown-based columns, and the Draft table prints the contract's internal id. Both are logged as known issues (section 11).

9The money math

Every figure in the Adjustment Summary, every over-run variation and every close-out credit comes from one formula. Knowing it lets you predict what Deep Space will raise before the customer asks.

Net adjustment to the contract sum
net adjustment = actual cost + margin − allowance (sell)
On actual cost: margin = actual cost × rate
On variance: margin = (actual cost − allowance) × rate

Actual cost is the cost of the approved drawdowns. Allowance is the allowance's sell value as priced into the contract. Rate is the contract's Provisional Sum Rate (% on cost), or the allowance's override. A positive result is an over-run and raises a variation the moment it turns positive; a negative result is a saving and is credited only at close-out; zero raises nothing. A rate of 0 models contracts that pay the actual cost with no margin.

One allowance, both bases

The allowance is PS-Asher1-0022's: $1,000 cost priced at 20% on cost, so $1,200 on the contract. The rows are four different totals of approved drawdown cost.

Approved drawdown costOn actual costOn variance
MarginNet adjustmentMarginNet adjustment
$700 (closed under)$140−$360 → PSC credit at close−$100−$600 → PSC credit at close
$1,000$200$0 — exactly on−$40−$240 → credit at close
$1,200$240+$240 → PSO variation$0$0 — exactly on
$1,500$300+$600 → PSO variation$60+$360 → PSO variation

Read the two "exactly on" rows: under On actual cost the allowance is spent when its cost is spent ($1,000), because the margin is added on top of every dollar of cost. Under On variance the allowance is spent when its sell is spent ($1,200), because the contract sum already carries the margin and only the difference is marked up. That is also why drawdown lines prefill with the contract's rate under one basis and as cost passthrough (sell = cost) under the other (section 5). The $1,500 row is the over-run you captured in section 5: the form warned Over the remaining allowance by $600.00 for exactly this reason.

Reading the six lines

LineWhat it is
1. Original allowanceThe allowance's sell value on the contract.
2. Actual purchase costCost of the approved drawdowns' work lines.
3. Builder's marginThe margin on line 2 under the contract's basis.
4. Additional procurement costsLines ticked Additional procurement cost (freight, craneage, storage) on the drawdowns.
5. Margin adjustmentThe margin on line 4.
6. Net adjustment to contract sum(2 + 3 + 4 + 5) − 1. Positive is carried by PSO variations, negative by the PSC credit at close-out.

The footer Effective margin 20.0% vs contractual 20.0% compares the margin the drawdowns actually carry with the contract's rate; it turns red when the drawdowns were priced below the rate, which is the same signal the Margin check dialog gives at save time.

Under while open reads as zero

An open allowance that is under-spent shows Net adjustment to contract sum $0.00, not a negative figure: the saving is not a saving until the allowance is closed, because more drawdowns may come. The credit appears in the summary and as a PSC variation at close-out.

10Dialogs & guardrails

Every message a customer may quote back to you, what triggered it and what to do. Server messages reach the screen word for word.

MessageWhenWhat to do
Allowances
Assign a head contract first (Approve Allowance disabled)The allowance has no head contract — usually one seeded from the estimate.Assign here on the contract's Provisional Sums tab, or pick the contract in Edit Allowance.
Allowance line 2 needs a cost code from the project's cost structure before it can be approvedApprove Allowance with a line whose cost code is empty or not in the picker.Edit Allowance → Select cost code on that line.
Every allowance line needs a cost code … before the allowance can be attachedSame check on the server, e.g. a legacy code typed as free text.Same fix. "Attached" means approved.
Title is requiredCreate Draft / Save Changes with an empty title.Add a title; a blank single line description then defaults to it.
A per-PS margin basis is exceptional — ps_margin_basis_note is required …Advanced override chosen without a reason.Type the reason, or set the select back to Contract default.
This provisional sum has crystallised — its margin basis can no longer be changed.Changing the override after a variation has been raised.Not possible; the adjustment is already on the contract.
Resolve {n} outstanding drawdowns first / Resolve the outstanding drawdowns first — approve or decline every Draft/Pending request before closing the allowanceClose Allowance with a Draft or Pending drawdown.Approve or decline them, then close.
Close allowance — No further drawdowns can be recorded, and if it closed under, the difference is credited back to the contract sum.Closing.Confirm only when the work is finished; closing is final.
Drawdowns
Margin check — Effective margin X% is below the contractual Y% … / … above the contractual … may be disputed at the final account / … lines should be cost-passthrough (sell = cost), or the client is charged margin twiceSaving a drawdown priced off the contract's basis or rate.Advice, not a block. Save anyway if the pricing is intended.
Over the remaining allowance — This drawdown exceeds the remaining allowance by $…Saving a drawdown whose sell exceeds what is left.Continue saves a Draft; the variation is raised at approval (section 7).
This allowance has no cost code to inherit — set one on the allowance, or pick a cost code on each line / Line n needs a cost code from the project's cost structureCreating a drawdown under a legacy allowance without a code.Set the code on the allowance if it is still Unapproved, otherwise pick one per line.
Every drawdown line needs a cost code … Edit the drawdown and pick the cost code on each line.Approve or Submit for approval on such a drawdown.Edit the drawdown, pick the code, retry.
Only Draft drawdowns can be edited / … deletedEdit or delete after submission or approval.Pending: wait for the decision or have it rejected. Approved: it is part of the record.
Approved drawdowns cannot be declined; the revoke flow is not available yetDecline on an approved drawdown.No undo in v1; record a correcting drawdown or contact support.
This drawdown's over-run is carried by a generated variation — dispute that variation instead; it reverts the drawdown automatically.Decline on the drawdown that raised the over-run variation.Dispute the variation from the Variations register.
This allowance carries a legacy direct contract-sum adjustment. Regularise it into a variation (COM-1014) before approving further drawdowns.Rare: a pre-September-2026 allowance adjusted without a variation.Support runs the regularisation script; do not work around it.
Internal approval
Internal approval required — This workspace routes PS drawdown approvals through the Delegation of Authority workflow …Approve on a workspace with an active PS Drawdown workflow.Submit for approval; the final approver's sign-off approves it.
This drawdown already has an approval in progress.Submitting twice.Act on the open route instead.
This drawdown has an internal approval in progress — revoke or resolve it in the approvals centre before declining.Decline while a route is open.Reject it in the Approval Route (or My Approvals), which returns it to Draft.
This project has no Delegation of Authority of its own yet, so the workspace default was used.Opening the Approval Route.Information only; a project-level workflow is optional.
You are not an approver on this step, but you hold Highest Authority — you can override it.A Highest Authority holder opens a route they are not on.Override Approve / Override Reject with a comment; recorded in the history.
This approval is complete, but the … status could not be updated automatically …The engine approved but the drawdown update failed.Refresh; if the chip stays In approval, contact support — the approval is recorded.
Variations, budget and claims
This variation was generated by a provisional sum drawdown and cannot be reverted to Draft. Dispute it instead.Revert to Draft on a PSO / PSC variation.Dispute it; the drawdown reverts automatically.
Draft Provisional Sums not in budget: $… · n drafts · n unassignedUnapproved allowances exist.Expected until they are approved; the amount is their cost.
Budget Register PS columns "don't match" the registerThe View As lens (PM 90%, CA 81%, JCA 73%).Switch to View As: CM before comparing.
claim_value must be 0 until the provisional sum line is approvedClaiming an allowance row with no approved drawdown.Approve a drawdown first.
… would take the line's certified-plus-claimed total to … outside the line value range …Claiming past the drawn cap on an allowance row.Claim up to Drawn; the over-run goes through its variation.

11Known limits and what is next

Not in this release

Known issues being worked

Recognising a legacy allowance

Its drawer shows Scope Lines rather than Allowance Breakdown, the Drawdowns section may read "This allowance predates the drawdown ledger — approve or decline its scope lines below, or add a drawdown to switch it to the ledger", and Drawn is the sell of its approved lines. In customer workspaces these are test records; in doubt, ask before touching them.

Appendix · Figure index

Every figure in the guide and where it was captured, in reading order. All captures are from the Asher1 demo project, September 2026.

#FileWhereWhat to show
0101-register-allowances.pngCommercial → Provisional SumsAllowances tab. Done.
0202-register-drawdowns.pngCommercial → Provisional SumsDrawdowns tab with Approve / Decline, In approval and Allowance actions. Done.
0303-allowance-drawer.pngAllowance drawerHeader cards, Close Allowance, Add Drawdown, first cards. Done.
0404-drawer-drawdown-cards.pngAllowance drawerApproved cards and a Pending card with the approval panel. Done.
0505-drawer-adjustment-summary.pngAllowance drawerAdjustment Summary and Allowance Breakdown. Done.
0606-company-settings-ps-margin-basis.pngAdmin → Company Settings → CommercialProvisional Sums card, house-default select open. Done.
0707-head-contract-form-ps-margin.pngHead Contract Register → New ContractProvisional Sum Margin Basis open + Provisional Sum Rate (% on cost). Done.
0808-head-contract-form-ps-margin-locked.pngEdit Head Contract (contract with an approved drawdown)Basis select disabled, "Locked" hint. Done.
0909-doa-ps-drawdown-workflow.pngAdmin → Finance → Delegation of Authority → Approval WorkflowsPS Drawdown workflow open. Done.
1010-estimation-boq-item-type-ps.png + 10b-estimation-edit-item-type.pngPreconstruction → Estimation → BOQ BuilderPS-typed BOQ line; Edit Item with Item Type. Done.
1111-budget-register-draft-ps-banner.pngCommercial → Budget RegisterDraft Provisional Sums banner + PS cost columns. Done.
1212-new-allowance-form.pngRegister → New AllowanceForm filled with contract facts and one priced line. Done.
1313-cost-code-picker.pngNew Allowance → Select cost codePicker open. Done.
1414-register-unassigned-draft.png + 14b-hc-tab-unassigned-drafts.pngRegister; head contract → Provisional Sums tabUnassigned chip; Unassigned Draft Provisional Sums with Assign here. Done.
1515-drawer-unapproved-approve-allowance.pngRegister → drawer of an Unapproved allowanceApprove / Decline Allowance + Edit Allowance panel. Done.
1616-hc-sov-preview-ps-badges.pngHead contract → Details → Schedule of Values PreviewPS · ACTIVE rows and PS rows. Done.
1717-new-drawdown-pick-allowance.png + 17b-new-drawdown-form-empty.pngRegister → New DrawdownAllowance picker; the form as it opens. Done.
1818-new-drawdown-form.pngNew Drawdown formFilled line, Remaining after $840. Done.
1919-new-drawdown-over-remaining.png + 19b-over-remaining-dialog.pngNew Drawdown formOver the remaining allowance total; the dialog. Done.
2020-drawdown-card-draft-actions.pngAllowance drawerDraft card with Approve / Decline / Edit / Delete. Done.
2121-internal-approval-required-dialog.pngDrawdown → Approve (DoA workspace)Internal approval required dialog. Done.
2222-approval-route-highest-authority.png + 22b-approval-route-override-approve.pngReview & approve / View approval routeApproval Route as Highest Authority; override with comment. Done.
23—Top bar → My ApprovalsSkipped: the inbox is described in section 6 and shown in the DoA engine's own guide.
2424-approval-route-override-reject.png + 24b-drawdown-card-approval-rejected.pngApproval Route; allowance drawerOverride Reject; card back in Draft with Approval rejected. Done.
2525-drawdown-approved-adjustment-summary.pngAllowance drawerAfter approval: Drawn / Remaining moved, Adjustment Summary. Done.
2626-drawer-variations-raised.pngRegister → PS-Asher1-0018 drawerVariations raised block + Adjustment Summary (+$120). Done.
2727-variations-register-source-filter.pngVariations (Client-Side)Source = From provisional sums; PSO / PSC pills. Done.
2828-variation-sidebar-raised-from.pngHVO-Asher1-0022 → Scope & PricingRaised from allowance + Adjustment Summary. Done.
2929-close-allowance-dialog.pngAllowance drawer → Close AllowanceThe dialog. Done.
3030-closed-allowance-credit.png + 30b-variations-register-psc-row.pngRegister → PS-Asher1-0017; Variations registerPSC credit in the drawer block; its register row. Done.
3131-budget-register-ps-columns.png + 31b-budget-register-cost-code-variations-tab.pngBudget Register → CC-7142PS columns under the PM lens; the cost code's Variations tab. Done.
3232-new-claim-header.png + 32b-new-claim-provisional-sums-section.pngProgress Claims → New Claim (active contract)Claim header; Section C with active and Pending approval rows. Done.