WIP report: Period Activity
Cost Forecasting to WIP, Part E. The Period Activity view shows what moved in one month for every project: cost booked, claims billed, margin recognised, and how those take WIP from its opening figure to its closing figure.
1The 60-second brief
The WIP report has two views. Position shows where each project stands to date. Period Activity shows what happened in one period, and proves that the movement adds up.
One row per project, one period at a time. Pick the open period or any closed period.
Cost is split by reporting class. Labour, Subcontract, Materials, Plant & Equipment and Other cost come from the reporting class set on each cost type.
The bridge must add up. Opening WIP + Billed − Cost − Margin recognised = Closing WIP. Anything left over is shown as Unexplained, and it should be 0.00.
A closed period does not change. Close period saves the figures and the transactions behind them. Later work lands in the next open period.
The view is for Commercial Managers, Financial Controllers and anyone who reconciles WIP to the accounts at month end.
2Month end: which date does what
A subcontract claim and its payment schedule carry several dates. Only two of them decide which month cost lands in: Received on the claim sets the claim's cost period, and the Posting date on the payment schedule or supplier invoice is the date sent to Xero as the bill date, with the cost period following it.
| Date | Where you see it | What it does |
|---|---|---|
| Date Served | Subcontract claim (Claim date on New Claim) | The date the subcontractor served the claim. It does not set the cost period. |
| Received | Subcontract claim | When the claim reached you. It defaults to the moment the claim is created, so change it if the claim arrived earlier. It sets the claim's cost period. |
| Claim period | Subcontract claim | The dates the work was done in. It does not set the cost period. |
| Posting date | Payment schedule, supplier invoice | Sent to Xero as the bill date, and the cost period follows it. The invoice date and the due date do not change. |
| Schedule Due, Payment Due | Payment schedule | The statutory schedule deadline and the payment date. They do not affect the cost period. |
Enter claims with the right Received date. If an October claim is keyed in during November, change Received to the day it arrived. Left at today's date, it counts in November and shows a LATE badge.
Check the Posting date before pushing to Xero. The payment schedule shows the Posting date with its cost period next to it. Use Change to set a different date. A reason is required, every change is logged, and a date in a closed commercial period is refused.
Mind Xero's lock date. Deep Space holds back a push dated on or before the lock date set in Xero. See Xero lock date: when Deep Space holds back a bill.
Fix a claim that landed in the wrong month
- Deep SpaceOpen the claimThe claim header shows Date Served, Received and Cost Period. A claim counted after its own month was closed shows a LATE badge (Late: period closed).
- Deep SpaceClick Move next to the cost periodPick another open cost period and enter a reason. The move is logged. Move only shows for users with the Move commercial period permission, which is off by default, so an admin may need to tick it in Security first.
- Deep SpaceCheck the Xero date as wellMoving the cost period changes the reporting in Deep Space only. If the bill in Xero should be dated in that month too, change the Posting date on the payment schedule before it is pushed to Xero.
Changing the cut-off day or close window
The cut-off day and close window have a workspace default in Company Settings, and a project can override them in Project Settings. Saving a change in Project Settings re-checks that project's subcontract claims and supplier invoices and shows how many moved cost period. Changing the workspace default re-checks every project (admin or workspace manager only). Closed periods and records that were moved by hand are never changed.
3Open the Period Activity view
-
Deep SpaceOpen the WIP reportReporting → Cost to Complete → Work in Progress (WIP).
-
Deep SpaceSwitch to Period ActivityAbove the table, click Period Activity next to Position. The table changes to one row per project for the selected period.
-
Deep SpacePick the periodThe period picker starts on Open period (live). Choose a closed month, for example Nov 2026 · closed, to see that month as it was reported.
-
Deep SpaceNarrow the listUse the search box, the Department (Branch) filter and the Active / On Hold / Archived switch, the same as on the Position view.
The line under the toolbar states the basis of the figures: the period, the workspace default cost period basis and cut-off, how many projects use their own cut-off, when the opening position was saved, and the currency (ex GST). For example: Cost period basis, workspace default: cut-off month end, close window 0 days · 2 projects use their own.
A project set up with its own cut-off day or close window shows an Own cut-off · cut-off 25th · close window 0 days label under its name, the same label as on the Position view.
A project that has never been closed can have cost in months before the selected one. That cost is already in its Closing WIP, but it is not part of this period. The row says how much, for example NZ$5,000.00 from earlier months (never closed) is in Closing WIP, and the transactions panel lists it on its own tab (section 8).
4Read a project row and the WIP bridge
Each row reads left to right in three groups.
| Group | Columns | What it tells you |
|---|---|---|
| Cost this period by reporting class | Labour $ / hrs, Subcontract, Materials, Plant & Equipment, Other cost, Total cost | Cost that started to count as an actual in this period, split by the reporting class of its cost type. Labour also shows timesheet hours. |
| Billing | Billed, Retention | Head contract claims certified in this period, and the retention held on them. |
| WIP bridge | Opening WIP, Margin recognised, Revenue earned, WIP movement, Closing WIP, of which late in, Unexpl. | How the period takes WIP from the opening figure to the closing figure. |
Opening WIP is the closing figure saved when the previous period was closed. Closing WIP for the open period is the live position; for a closed period it is the saved one.
Use Columns to switch the cost columns from Reporting class to Cost type when you want one column per cost type instead.
Hover it to read the note for that project. Typical notes: part of the cost is on cost codes outside the Budget Register, or a cost type could not be matched. The figures are still shown; the note tells you what to check.
5Set reporting classes on cost types
The cost columns follow the reporting class of each cost type. Set it once per cost type. It only affects the Period Activity view: it does not change the Budget Register, forecasts or the Xero mapping.
-
Deep SpaceOpen the cost typesAdmin → Finance → Financial Model → Cost Types tab.
-
Deep SpaceChoose a class for each cost typeIn the Reporting class column pick Labour, Subcontract, Materials, Plant & Equipment, Other cost or Not a cost. The choice saves as soon as you pick it.
-
AutomaticThe report followsThe next time you open the Period Activity view, cost on that cost type sits in the matching column.
| Class | Use it for |
|---|---|
| Labour | Your own workforce: wages and timesheet cost. |
| Subcontract | Subcontractors and labour hire. |
| Materials | Materials, sundries and consumables. |
| Plant & Equipment | Plant, equipment and hire. |
| Other cost | Real cost that fits none of the above, for example fees or insurance. |
| Not a cost | Budget lines that are not spend, for example margin, contingency or provisional amounts. |
Deep Space fills the class for you when a cost type has a standard name: Labour and Internal Labour; Subcontract and External Labour; Materials and Sundries & Consumables; Hire and Plant; Margin, Contingency and Provisional. Any other name stays Unclassified until you choose.
Cost on an unclassified cost type is in Total cost and in the bridge. It appears in an Unclassified column, and the project is counted by the Unclassified cost type chip. Classify the cost type to move it into the right column.
6Close a period and get a checked month
Closing a period saves each project's WIP position for that month, together with the transactions that made up the month. That saved set is what makes the next month checkable.
-
Deep SpaceApprove the monthly forecastsA period closes only for projects whose monthly forecast for that month is approved. Projects without an approved forecast stay open.
-
Deep SpaceClose the periodOn the WIP report click Close period, choose the Period to close, then click Close Nov 2026 (the button names the month you chose). The list goes up to the current month: a month that has not started cannot be closed, and its monthly forecast cannot be approved until it starts.
-
AutomaticDeep Space reports what closedThe result lists the projects that closed, the projects still open because their forecast is not approved, and any that were skipped (for example no head contract). The closed month then appears in the period picker as Nov 2026 · closed.
What the Unexplained column shows
| You see | It means | What to do |
|---|---|---|
| — and “No closed period before this one” | This is the project's first period on the report. There is no opening position to bridge from. | Nothing. Close this period; the next one is bridged. |
| Not checked | The previous period was closed before Period Activity existed, or its saved transactions are not available, so the movement cannot be proven line by line. | Close the current period. That saves a starting point, and the following period is checked. |
| 0.00 in green | Checked. Every dollar of the movement is explained by a transaction in the period. | Nothing. |
| An amount in red | Checked, and part of the movement is not explained. | Open the project's transactions (section 8) and contact Deep Space support with the project and period. |
Expect Not checked or — in the first month you use the view. After one Close period, every later month shows a checked figure.
On a closed period the toolbar shows Reopen… and Version history instead of Close period. A reopened period is closed again as the next version. If an earlier period is re-closed after a later one, the later project row asks you to re-close that period to restore the check.
7Late in and the other filter chips
The chips above the tiles count the projects that have each condition. Click a chip to show only those projects.
| Chip | Meaning |
|---|---|
| Late in | Cost that reached the books after its own month was closed, so it landed in this period. Example: a subcontract claim for October entered after October was closed counts in November. The amount is also shown in the of which late in column; it is already included in Cost this period. |
| Xero month differs | Cost whose Xero date falls in a different month than the period it is counted in. |
| Prior-period adjustments | Changes to transactions of earlier, closed periods. The change is counted in this period; the closed period keeps its reported figures. |
| Unclassified cost type | Cost on a cost type that has no reporting class yet (section 5). |
| Week spans month-end | Timesheet weeks that run across the month end. |
| Unexplained ≠ 0 | Checked projects where the bridge leaves an amount that no movement explains. |
8See the transactions behind a figure
-
Deep SpaceClick the projectClick the project code in the first column. A panel opens with the project's bridge for the period: Opening WIP, + Billed, − Cost, − Margin recognised, = Closing WIP.
-
Deep SpaceChoose a tabCost lists every cost transaction of the period, Billing the certified head contract claims, Adjustments the changes to earlier periods. Each tab shows its row count. A project that has never been closed can also show Earlier months (never closed): cost from months before this one, already in Closing WIP and not in Cost this period.
-
Deep SpaceFilter and open the documentFilter by Class or Source, or click the Xero month differs and Late in chips. Click a document number to open the claim or invoice.
Sources you can see on the Cost tab: subcontract claims, supplier invoices, timesheet weeks, credit notes, manual entries and cost transfers. The tab total always equals the project's Total cost in the table.
9Export the summary and the transactions
| Button | What you get | Use it for |
|---|---|---|
| Export summary CSV | One line per project plus a Total line: Opening WIP, each reporting class, Total cost, Labour hours, Billed, Retention, Margin recognised, Forecast change, Revenue earned, WIP movement, Closing WIP, Late in, Prior-period adjustments, Unexplained. | The month-end WIP journal and management reporting. |
| Export transactions CSV | One line per transaction for every project in the period: source, document ref, counterparty, cost code, cost type, reporting class, amount, hours, dates, cost period and the reason it was moved, Xero ref and status, and the flags. | Reconciling to Xero and answering "what is in this number". |
Sum the Amount column of the transactions file by project and reporting class: the totals equal the class columns of the summary file. Both exports follow the period you have selected.
10Not checked, Unexplained and other questions
Why does every project show Not checked?
Close period closed nothing, or only a few projects. Why?
A claim dated last month shows in this month. Is that wrong?
Why is there cost in an Unclassified column?
Total cost is higher than the class columns added together. Why?
Do figures for a closed period change when I keep working?
Unexplained is not zero. What should I do?
11When does a subcontract claim count as cost?
A subcontract claim counts as cost once lines on its payment schedule are approved. The claim then shows Certified or Partially Certified. A schedule that has only been issued (Issued) does not count yet, and neither does a claim still in Draft. This is the same rule the Budget Register uses for Actuals.
-
Deep SpaceOpen the payment scheduleFrom the Subcontractors menu, open the payment schedule issued for the claim (for example SPS-26007-0002 for claim SPC-26007-0002).
-
Deep SpaceApprove the linesGo to the Schedule of Values tab and click Approve on a line, or Approve all remaining. Approving sends nothing to the subcontractor and pushes nothing to Xero.
-
AutomaticThe cost shows on the WIP reportThe approved amount counts in the claim's cost period. The WIP report and Period Activity pick it up the next time the Budget Register recalculates, so allow for a short delay after approving.
Head contract claims follow the same idea on the billing side. A claim is billed in Period Activity once the client's payment schedule has been internally approved and Accepted. Recording the schedule (status Received) is not enough.