In this walkthrough, you'll set up and track retention in the Deep Space web app. We'll cover how retention works, setting it on a subcontract, sliding rates and value bands, and tracking and releasing what you hold. Then the questions we get most.
The full series: 26 videos in Builder's Wheel order (Win, Set Up, Build, Move the Money, Govern)
- Build an Estimate and Proposal Win
- Multi-Trade Tender Win
- Set Up Your Workspace Set Up
- Add Users and Give Them Access Set Up
- Company Settings: Get Your Documents Ready Set Up
- Connect Xero and Map Your Cost Codes Set Up
- Folder Templates and Project Documents Set Up
- Document Templates vs Contract Templates Set Up
- Email Templates and Sending Documents Set Up
- Head Contract Setup Set Up
- Build Your Programme Set Up
- Subcontracts: Award to Executed Set Up
- DS Site: Invites, Inductions and Site Sign-on Build
- Drawings to Site and Subbies Build
- Run Your Programme on Site Build
- RFIs, Notices and the Project Inbox Build
- Inbox to Xero: How the Money Flows Move the Money
- Purchase Orders Move the Money
- Process Supplier Invoices Move the Money
- Subbie Claims: Inbox to Payment Schedule Move the Money
- Retentions and Security Move the Money
- Variations, End to End Move the Money
- Provisional Sums: Allowances, Drawdowns and Over-runs Move the Money
- Progress Claims to Your Client Move the Money
- Budget and Forecasting Govern
- Delegation of Authority Govern
How retention works
Set it on the subcontract
Track and release
Common questions
Every claim shows zero retention.
The rate wasn't set on the subcontract. Set it before the subcontract is executed. If it's already executed, ask Deep Space support to set it and load what you've held to date.
The rate didn't change at Practical Completion.
PC rules apply from the date PC is recorded as reached in Key Dates, not the planned date.
Retention is being taken on variations.
Untick Include Variations in Retention on the subcontract.
I can't release retention yet.
Nothing is releasable until PC is recorded. Then the PC share can be released, and the rest at the end of the DLP.
Where does retention go in Xero?
Retention posts to the Retention Payable and Retention Receivable accounts you choose in Finance Integrations.
Quick reference
- Set the rate and cap under Security Settings
- Sliding retention: milestones, cap or value bands
- Automatic or manual retention control
- Subcontractor and Head Contract Retentions registers
- Release from PC, the rest at the end of the DLP