Video 22 of 28 · Move the Money

Retention Statements and Retention Liability

Set your retention trust account, send each subcontractor one statement across all projects, see Retention Liability, add opening balances and automate monthly or quarterly sends.

← Retentions and SecurityVariations, End to End →
Retention Statements and Retention Liability video thumbnail
Watch the Retention Statements and Retention Liability video on YouTube
Watch the video walkthroughhttps://youtu.be/Shn5NL53QI0

In this walkthrough, you'll set your retention trust account in Company Settings, choose who receives each statement, generate and send one statement per subcontractor across all projects, see everything you hold on Retention Liability, add retention held before Deep Space, and send statements automatically each month or quarter from Admin → Automation.

The full series: 28 videos in Builder's Wheel order (Win, Set Up, Build, Move the Money, Govern)
  1. Build an Estimate and Proposal Win
  2. Multi-Trade Tender Win
  3. Set Up Your Workspace Set Up
  4. Add Users and Give Them Access Set Up
  5. Company Settings: Get Your Documents Ready Set Up
  6. Connect Xero and Map Your Cost Codes Set Up
  7. Folder Templates and Project Documents Set Up
  8. Document Templates vs Contract Templates Set Up
  9. Email Templates and Sending Documents Set Up
  10. Head Contract Setup Set Up
  11. Build Your Programme Set Up
  12. Subcontracts: Award to Executed Set Up
  13. DS Site: Invites, Inductions and Site Sign-on Build
  14. Drawings to Site and Subbies Build
  15. Run Your Programme on Site Build
  16. RFIs, Notices and the Project Inbox Build
  17. Inbox to Xero: How the Money Flows Move the Money
  18. Purchase Orders Move the Money
  19. Process Supplier Invoices Move the Money
  20. Subbie Claims: Inbox to Payment Schedule Move the Money
  21. Retentions and Security Move the Money
  22. Retention Statements and Retention Liability Move the Money
  23. Variations, End to End Move the Money
  24. Provisional Sums: Allowances, Drawdowns and Over-runs Move the Money
  25. Progress Claims to Your Client Move the Money
  26. NZS 3910 Claims: On-site, Off-site, Materials and On Account Move the Money
  27. Budget and Forecasting Govern
  28. Delegation of Authority Govern

1The 60-second brief

A Retention Statement is one document per subcontractor. It lists every retention deduction you hold for them on every project in the workspace, as at a date you choose. Retention Liability is the same information for the whole business: every subcontractor, every project, one total.

Four rules that explain most behaviour

The figures come from the retention ledger. Retention is recorded when a subcontract payment schedule is accepted. The statement, Retention Liability and the Subcontractor Retentions register all read the same ledger, so they always agree.

One statement covers all projects. It is generated from the subcontractor's company record, not from a project.

Amounts are excluding tax, except the last column of the statement, which shows the payment including tax.

A statement goes to the subcontractor's Accounts contact. A subcontractor with no contact to send to is skipped and listed, never guessed at.

You want toGo to
Report to one subcontractorDirectory → Company Directory → open the company → Retentions tab
See everything you hold, or send to everyoneCommercial → Retentions + Security → Subcontractor Retentions → Retention Liability tab
Add retention held before Deep SpaceCommercial → Retentions + Security → Subcontractor Retentions → Add opening balance
Send on a scheduleAdmin → Automation
Set the trust account printed on statementsAdmin → Company Settings

2Set your retention trust account

The trust account is the bank account you hold subcontractor retention money in. It is printed on every Retention Statement, against each subcontract. Set it once.

  1. Open Company Settings
    Admin → Company Settings, then scroll to Retention trust account.
  2. Fill in the account
    Enter Bank Name, Branch and Account Name. Account Number is optional. Save the settings.
  3. Statements pick it up
    Every statement generated from now on prints a line such as “Bank: Example Bank Ltd, Auckland Commercial, Retention Money Trust Account” under each subcontract.
Company Settings, Retention trust account fields
Company Settings, Retention trust account. Bank Name, Branch, Account Name and the optional Account Number. The line is printed on Retention Statements; leave the fields blank to print no trust account line.
New Zealand workspaces

If the workspace country is New Zealand and no trust account is set, the Retentions tab on a company record shows a warning with a link to Company Settings. Set the account before you send statements.

3Choose who receives each statement

Deep Space sends a statement to the subcontractor's default contact for Accounts. Set this on the contact, once per subcontractor.

  1. Find the contact
    Directory → Company Directory → Contacts tab. Open the subcontractor's company to list its contacts, then choose View contact details on the person.
  2. Tick Accounts
    Choose Edit. Under Default contact for, tick Accounts, then Save. More than one contact can be a default for Accounts; each of them receives the statement.
The subcontractor hasThe statement goes to
One or more default contacts for AccountsThose contacts
No Accounts default, but a default contact for GeneralThe General default contacts
NeitherNo one. The subcontractor is skipped and listed as “No Accounts contact with an email address”.

When you send a single statement you can change the recipients in the Send dialog. When you send to everyone, or on a schedule, these defaults decide.

4Generate a statement for one subcontractor

  1. Open the subcontractor's Retentions tab
    Directory → Company Directory → open the company → Retentions tab. The tab shows the retention held for this company across every project, with one row per subcontract.
  2. Choose the statement date
    Set As at. Deductions and releases after that date are left out. The cards and the table update to match.
  3. Generate
    Choose Generate Retention Statement. In the Generate Document dialog, choose Show preview to check it, fill in Code if you use one, then Download PDF.
  4. Deep Space files a copy
    The PDF is downloaded and also filed in Documentation → Company Documents → Retention Statements, in a folder for that subcontractor. It appears under Statements generated on the tab.
Company record, Retentions tab
Company record, Retentions tab. The As at date, the Generate Retention Statement and Send Retention Statement buttons, the cards for Retention held, Subcontracts with retention held, Projects and Next release, and one row per subcontract with its deductions and retention held.
Generate Document dialog with the Retention Statement preview
Generate Document, Retention Statement preview. On the left, the Subcontractor Name and Statement Date from the statement and the Code field you can fill in. On the right, the statement as it will print: the six ledger columns, the trust account line under each subcontract, a Subcontract Total and the Total Tax Excl Retention Being Held.
The buttons are greyed out

Generate and Send are available only when the company has retention held at the As at date. Hover over a greyed button to see why.

5Reading the statement

The statement is a ledger grouped by project and subcontract. Each retention deduction is one row.

ColumnWhat it shows
DateThe date of the payment schedule the retention was deducted on.
Our ReferenceYour payment schedule number. For an opening balance, your own reference, or “Opening balance”.
Your Reference / Original Trans. ReferenceThe subcontractor's own claim or invoice reference, when one was recorded.
Original Tax Excl RetThe retention deducted on that row, excluding tax.
Remaining Tax Excl RetHow much of that deduction is still held. Releases are taken off the oldest deductions first.
Transaction Tax InclThe payment that row belongs to, including tax: the amount certified, less the retention withheld, plus any retention released on it. Blank when there is no payment schedule behind the row, such as an opening balance.
Subcontract Total = remaining retention on that subcontract Total Tax Excl Retention Being Held = the sum of every Subcontract Total
  • Releases print as their own row, with the amount in brackets and /R after Our Reference.
  • The heading shows who the statement is To, the Statement Date, your Code for the subcontractor and who it is From. Code is taken from the creditor code on the subcontractor's most recent claim and is blank when no claim has one.
  • Each page is numbered in the footer, for example “Page 1 of 2”.
  • The Total held matches Currently held for the same subcontracts in the Subcontractor Retentions register.
Changing the wording or layout

The statement is a document template. Edit it in Admin → Document Templates (Retention Statement). The email it is sent with is in Admin → Email Template Library. The notice at the top of the statement follows your workspace country.

6Send a statement and see its history

  1. Start the send
    On the company's Retentions tab, set As at and choose Send Retention Statement.
  2. Check the recipients
    The Send dialog fills in the subcontractor's default Accounts contact. Add or remove recipients if you need to, then send.
  3. Deep Space emails the PDF
    The statement is attached as a PDF. The row under Statements sent shows Sending, then Sent, usually within a few seconds.
Statements generated and Statements sent on the Retentions tab
Statements generated and Statements sent. Statements generated lists every filed statement with its Statement Date, when it was generated, by whom, its Version and an Open link. Statements sent lists each email with the Statement Date, who it was Sent to, when, and its Status.

Generating again for the same date files a new version of the same document. Open any version from the list.

7Retention Liability: what you hold across the business

Retention Liability shows the retention you hold for every subcontractor on every project. This is the figure your retention trust account has to cover.

  1. Open it
    Commercial → Retentions + Security → Subcontractor Retentions, then the Retention Liability tab at the top of the page.
  2. Read the totals
    The cards show Retention held, Subcontractors, Subcontracts with retention held and the Next release date. The table groups subcontracts under each subcontractor with Deducted, Released, Held and Next release.
  3. Search or export
    Type in the search box to narrow by subcontractor, project or subcontract; the cards and totals follow. Export to Excel exports what is shown, with a total per subcontractor and a grand total.
Retention Liability tab
Retention Liability. Send statements to all and Export to Excel at the top right; cards for Retention held, Subcontractors, Subcontracts with retention held and Next release; and the table of Project, Subcontract, Deducted, Released, Held and Next release grouped by subcontractor.
It covers all projects

This view does not follow the project selected in the header. It shows every project you can open. If you cannot open a project, its retention is not shown to you.

8Send statements to all subcontractors

  1. Open the list
    On Retention Liability, choose Send statements to all. Set the Statement date; it starts on the last day of the previous month.
  2. Check who will receive one
    The list shows every subcontractor with retention held, the amount, and who the statement will be sent to. Subcontractors that will not get one say Skipped and why. Nothing has been sent yet.
  3. Send
    Choose Send N statements. Each subcontractor is then marked Sent, Skipped or Failed. Each send also appears under Statements sent on that subcontractor's record.
Send Retention Statements to all subcontractors dialog
Send Retention Statements to all subcontractors. The Statement date, the count of statements that will be sent and subcontractors skipped, and one row per subcontractor with Retention held and Sent to. A skipped row reads “Skipped: No Accounts contact with an email address”.
The button is greyed out

A statement covers every project a subcontractor works on. If some retention sits on a project you cannot open, you cannot send to all, because your statements would leave that project out. Ask someone with access to every project to send them.

9Add retention held before Deep Space

If you already held retention on a subcontract before you managed it in Deep Space, add it as an opening balance. It is then counted in the register, on the subcontractor's statement and in Retention Liability.

Before you start

The project and the subcontract must exist in Deep Space, and the subcontract cannot be Draft or Cancelled.

Check the amount against your accounts first. An opening balance is reported to the subcontractor as money you hold for them.

  1. Open the register for the project
    Select the project in the header, then Commercial → Retentions + Security → Subcontractor Retentions. Choose Add opening balance at the top right.
  2. Enter the balance
    Pick the Subcontract. Enter Retention held (excl tax) and the Held as at date, which cannot be in the future. Your reference is optional, for example the job ledger number in your previous system; it prints as Our Reference on the statement.
  3. Save
    Choose Add opening balance. The subcontract's Currently held increases by that amount. Deep Space records who entered it and when.
Subcontractor Retentions register with Add opening balance
Subcontractor Retentions register. The Add opening balance button at the top right, and the register columns Subcontract, Subcontractor, Contract value, Retention settings, Total retention, Currently held and Next release.
Add opening balance dialog
Add opening balance. Subcontract, Retention held (excl tax), Held as at, Your reference and Note. The balance is added to the retention held and appears on the subcontractor's Retention Statement.

On the statement, an opening balance is a row dated Held as at, with your reference under Our Reference and no Transaction Tax Incl amount.

10Send statements automatically

Deep Space can send every subcontractor their statement on a schedule, monthly or quarterly. Set it up in two parts: a trigger that says when, and a step that says what.

Set it up

  1. Create the trigger
    Admin → Automation. Under Triggers choose New and pick Monthly Retention Statements (Workspace). Set the Timezone, the Day of month and the Send time, then Create Trigger.
  2. Add the step
    Select the trigger, choose New Bundle, open it and choose Edit. Choose Add retention statement step.
  3. Choose how often
    Monthly sends every month, as at the end of the month before. Quarterly sends in January, April, July and October only, as at the end of the quarter before.
  4. Leave Mode on Dry run and save
    A new step starts as a Dry run: it emails no one. Choose Save.
Automation, Send Retention Statements step
Automation, Send Retention Statements step. The Monthly Retention Statements trigger on the left and the step on the right with How often (Monthly or Quarterly) and Mode (Dry run or Send). Add retention statement step adds the step to a bundle.

Test it, then switch it on

  1. Run a dry run
    On the bundle choose Run, then Run Now. The dialog says this is a dry run and that nothing is emailed.
  2. Read Recent runs
    Open the bundle. Recent runs lists who would be sent a statement, with their email address, and who would be skipped and why. Fix any missing Accounts contacts and run it again.
  3. Switch to Send
    When the list is right, edit the step, set Mode to Send and save. Make sure the trigger and the bundle are both on.
Automation bundle, Recent runs for Send Retention Statements
Recent runs. Each run says whether it was a dry run or emailed, who it would send to or was sent to with their address, and the subcontractors skipped, grouped by reason: no Accounts contact, or no retention held at the statement date.
Safe to run again

A statement is not sent twice to the same subcontractor for the same statement date. If a run is repeated, subcontractors who already received that statement do not get it again. A statement that failed to deliver is sent on the next run.

Running it by hand

Run on the bundle runs the step straight away, in whatever Mode it is set to. A manual run sends even when the step is set to Quarterly and it is not a quarter month.

11Troubleshooting

A subcontractor was skipped: “No Accounts contact with an email address”
No contact at that company is a default contact for Accounts or for General. Tick Accounts under Default contact for on the right person (see section 3), then send again.
A subcontractor was skipped: “No retention held at the statement date”
All of their retention was deducted after the statement date, or it has all been released. Nothing is owed a statement for that date.
The statement total does not match what I expect
Check the As at date first: movements after it are left out. Then compare with Currently held in the Subcontractor Retentions register for the same subcontracts. If retention was held before you used Deep Space, add it as an opening balance (section 9).
There is no trust account line on the statement
The Retention trust account in Admin → Company Settings is blank. Fill it in (section 2) and generate the statement again.
Code is blank on the statement
Code comes from the creditor code on the subcontractor's most recent claim. If no claim has one, type the code into the Code field in the Generate Document dialog before you download.
Send statements to all is greyed out
Either no retention is held, or some retention sits on a project you cannot open. Hover over the button to see which.
The scheduled send did nothing this month
Check three things in Admin → Automation: the trigger is on, the bundle is on, and the step's Mode is Send. A step set to Quarterly sends only in January, April, July and October; Recent runs says so on the other months.
I entered an opening balance with the wrong amount
An opening balance cannot be changed or removed from the register. Contact Deep Space support with the subcontract and the correct amount.