A guided, one-click-at-a-time walkthrough: the two dates that matter, setting your cut-off and close window, entering claims with the right Received date, the Move commercial period permission, moving a claim, the Posting date and Xero lock date, and checking the month in Period Activity.
The full series: 29 videos in Builder's Wheel order (Win, Set Up, Build, Move the Money, Govern)
- Build an Estimate and Proposal Win
- Multi-Trade Tender Win
- Set Up Your Workspace Set Up
- Add Users and Give Them Access Set Up
- Company Settings: Get Your Documents Ready Set Up
- Connect Xero and Map Your Cost Codes Set Up
- Folder Templates and Project Documents Set Up
- Document Templates vs Contract Templates Set Up
- Email Templates and Sending Documents Set Up
- Head Contract Setup Set Up
- Build Your Programme Set Up
- Subcontracts: Award to Executed Set Up
- DS Site: Invites, Inductions and Site Sign-on Build
- Drawings to Site and Subbies Build
- Run Your Programme on Site Build
- RFIs, Notices and the Project Inbox Build
- Inbox to Xero: How the Money Flows Move the Money
- Purchase Orders Move the Money
- Process Supplier Invoices Move the Money
- Subbie Claims: Inbox to Payment Schedule Move the Money
- Retentions and Security Move the Money
- Retention Statements and Retention Liability Move the Money
- Variations, End to End Move the Money
- Provisional Sums: Allowances, Drawdowns and Over-runs Move the Money
- Progress Claims to Your Client Move the Money
- Month-End Cut-Off: Which Date Does What Move the Money
- NZS 3910 Claims: On-site, Off-site, Materials and On Account Move the Money
- Budget and Forecasting Govern
- Delegation of Authority Govern
The two dates that matter
A subcontract claim carries several dates. Here's an example claim, opened from the Progress Claims page.
Date Served is the day the subcontractor served the claim.
Received is the day it reached you. Received is the date that sets the cost period: the month the cost counts in on your WIP report.
The second date that matters is the Posting date on the payment schedule. We'll look at that in chapter six.
Set your cut-off and close window
First, check your cut-off settings. You only need to do this once, and you'll need admin access.
In the left-hand menu, look right at the bottom. Click the small arrow to show the lower menu, then click Admin.
The Admin menu opens. Click Company Settings.
Along the top of Company Settings, click the Commercial tab.
Scroll down to the section called Commercial cut-off.
Box one is the cut-off day. A claim received on or before this day counts in the month it's dated. Leave it blank to use month end.
Box two is the close window. It gives you extra days after month end.
For example, with a close window of ten days, an October claim received by the tenth of November still counts in October, as long as October is still open.
These are the workspace defaults. A project can have its own, under Project Settings, General.
Anything received after the cut-off and the close window rolls into the next open month, with a LATE badge.
Enter a claim with the right Received date
Now let's enter a claim. In the left-hand menu, click Commercial, then Subcontractors, then Progress Claims from Subcontractor.
Check the project in the bar at the top of the screen. The claims listed are for the project shown there.
The Cost Period column shows the month each claim counts in. This one shows November, with a LATE badge.
To add a claim, click New Claim, at the top right.
In the New Claim form, Claim date is the date the subcontractor served the claim.
Just below, on the left, is Received. It fills in today's date and time automatically.
If the claim actually arrived earlier, change Received to that day. This is the step that keeps an October claim in October.
Then fill in the rest of the claim as normal.
Give finance the Move permission
Sometimes a claim still lands in the wrong month. To move it, a user needs the Move commercial period permission, and it's off by default.
An admin turns it on. Go back to the Admin menu, and this time click Security.
On the left is the list of roles. Click the role that should be able to move claims, for example your accounts or finance role.
On the right, scroll down through the Commercial features until you find Move commercial period.
Tick the box in the View column.
Then click Save, at the top right.
People with that role need to refresh their browser before the change shows up.
Move a claim to the right month
Back on Progress Claims, click a claim to open it.
Next to the cost period you'll see the LATE badge, and a blue Move link. Click Move.
The Move commercial period box opens. At the top, it shows the current period, and why the claim landed there.
In Move to, pick the month the claim belongs in. Check it carefully, as the list may not start on the month you want.
Only open months are listed. If the month you need is closed, it has to be reopened from the WIP report first.
Type a short reason. It's recorded with your name. Then click Move period.
Moving the cost period only changes reporting inside Deep Space. Due dates and the Xero date don't change.
Check the Posting date before Xero
Next, the payment schedule. In the menu, under Subcontractors, click Payment Schedules Issued.
Then click the schedule number to open it.
Scroll down to Schedule Details. The Posting date is sent to Xero as the bill date, and the cost period follows it. You can see the cost period written underneath.
Payment Due is a separate date. It's the date to pay the subcontractor by, and the Posting date doesn't change it.
To change the Posting date, click Change.
Pick the new date, type a reason, and click Save. A date in a closed month is refused.
Do this before the schedule goes to Xero.
If the Posting date is on or before the lock date set in Xero, Deep Space holds the bill back and shows Xero locked. Pick a later Posting date, and push again.
Check the month in Period Activity
Finally, check the month. In the menu, click Reporting, then Cost to Complete, then Work in Progress.
Above the table, click Period Activity.
The line at the top shows your cut-off and close window, and how many projects use their own.
Late in counts claims and invoices that arrived after their month was closed. Click it to see which projects they're on.
Xero month differs shows cost where the Xero date is in a different month from the cost period.
And Unexplained should be zero. When it is, the month ties out.
Common questions
Does the cost period change when the subcontractor gets paid?
No. The cost period is for reporting inside Deep Space. Pay against the Payment Due date on the payment schedule.
Why does the Xero bill show November when I moved the claim to October?
Moving the claim changes Deep Space reporting only. The Xero bill date comes from the Posting date, so change that before the schedule goes to Xero.
I can't see the Move link. Why?
Your role needs the Move commercial period permission. Ask an admin to tick it under Admin, Security, then refresh your browser.
Can I move a claim into a closed month?
No. Closed months aren't offered. Reopen the month from the WIP report first, if your finance team agrees.
Most of our claims come in during the first week of the next month. What should we do?
Set a close window in Company Settings, for example ten days, so those claims stay in the claim month.
Quick reference
- Received sets a claim's cost period. Change it if the claim arrived earlier.
- Set the cut-off day and close window in Admin, Company Settings, Commercial.
- Tick Move commercial period for finance roles in Admin, Security.
- Fix a late claim with the Move link next to its cost period.
- The Posting date is the Xero bill date. Check it before the push.
- Check Late in and Unexplained in Period Activity before you close.
- Written detail: WIP Report: Period Activity, section 2 and Xero lock date